3. Project Plan & Schedule

The project plan determines itself from the given time plan and from the implementation of the following duties:

Administrative duties:

▶ Development of a common flow chart
▶ Development and implementation of a common working platform
▶ Development of a common schedule of the realisation
▶ Development of a requirement catalogue for the test group
▶ Development of an evaluation sheet for the test group

Content duties:

▶ Development curriculum for web based learning modules
▶ Development curriculum for virtual classrooms
▶ Development curriculum for the attendance training

Duties for the project realisation

Based on the curricula and the organisational duties, the following elements should be implemented:

▶ Development and implementation of the web based learning modules
▶ Definition of the test group
▶ Definition of the realisation schedule for the test group
▶ Division and training of the trainers for the virtual classrooms
▶ Division and training of the trainers for the attendance training
▶ Organisation of the attendance training
▶ Organisation of the examination board
▶ Certification


3.1 Key Aspects

For a successful fulfilment of the project aims it is essential to give special attention to the following key aspects:

▶ Strong teamwork
▶ Short response times in communication
▶ Quality of all curricula
▶ A promptly implementation of the (technical) web components
▶ Continuous and accompanying evaluation
▶ Instruction of trainers and test group
▶ To keep to the schedule


3.2 Milestones

In the following are shown the milestones out from the duties and the given schedule.

Aug 2009
Project Start
Sept 2009: Implementation of the Project Management platform;
German language training curriculum for training modules;
Dec 2009:
First prototypes of the web learning module;
Feb 2010
Training curriculum for virtual classroom training;
Test run web learning modules;
Mar 2010:
Definition tests & examinations;
Train the Trainer for VCRT;
Start test group;
Sept 2010:
Train the Trainer for attendance training;
Oct 2010: Start Attendance Training;
Nov 2010:
Evaluation results from test group / web based training;
Dec 2010:
Final Exam & Certification test group;
Feb 2011
Final Evaluation from test group
Mar 2011: Project Final Report
Jun 2011: Project Summary Presentation
Jul 2011: Project End


3.3 Mobility Plan

To the accompanying project coordination the following mobility plan was developed.

This plan should serve as an orientation for the necessary mobility and shows a suitable time frame for the realisation.

Date

Topic

Partner

Meeting in

Objectives

mobilities

Aug 2009

Preparation
Project Start

INKA,
GPOCS

Nendeln FL

Re-organisation Partners,
Roles, Preparation

I(1)

Sept 2009

Training
Curriculum

INKA,
GPOCS

Dornbirn AT

prepare german lang.
training curriculum

G(1)

Oct 2009

Organisational
meeting

OKAN, INKA,
GPOCS

Istanbul TR

redefine roles, duties &
responsibilities,timeplan

I(1), G(1)

Nov 2009

Preparation web
learning modules

INKA,
GPOCS

Nendeln FL

collecting material,
develop narration book

I(2)

Dec 2009

Prototype web
learning module

INKA,
GPOCS

Dornbirn AT

cross-check of prototype
web learning module

G(1)

Jan 2010

Preview

OKAN, INKA,
GPOCS

Dornbirn AT

Presentation, 1st check
web based training
modules

O(3), G(1)

Feb 2010

Virtual Classroom
Training (VCRT)

INKA,
GPOCS

Dornbirn AT

Definition training guide 
curriculum in VCRT

G(1)

Mar 2010

Train the Trainer
(VCRT)

OKAN, INKA,
GPOCS

Istanbul TR

Train the Trainer (VCRT),
start with testgroup

(I1), G(1)

Mar 2010

Preparation Tests,
Examinations

INKA,
GPOCS

Dornbirn AT

Definition tests &
examinations

G(1)

May 2010

Intermediate
meeting

OKAN, INKA,
GPOCS

Nendeln FL

First exchange of
experiences with
testgroup

O(3), I(1)

Sept 2010

Train the Trainer
attendance train.

OKAN, INKA,
GPOCS

Dornbirn AT

Train the Trainer for
attendance training

O(3), G(1)

Oct 2010

Start Attendance
Training, Classr.

OKAN, INKA,
GPOCS

Istanbul TR

Start Attendance Training
with testgroup, 10 days

I(1), G(1)

Nov 2010

Evaluation
web-based
Training

INKA,
GPOCS

Dornbirn AT

Evaluation, appraisal of
results from testgroup

G(1)

Dec 2010

Exam & Certifcate
Testgroup

OKAN, INKA,
GPOCS

Istanbul TR

Final Examination,
Certifi-cation with
testgroup

I(2), G(1)

Mar 2011

Project Final
Report

OKAN, INKA,
GPOCS

Nendeln FL

Developing final project
report

O(3), I(2)

Jun 2011

Final Project
Meeting

OKAN, INKA,
GPOCS

Istanbul TR

Final meeting with
Project Partners

I(1), G(1)

Out of this plan the following mobilities were planned for the project partners:

Organisation

In Austria

In Liechtenstein

In Turkey

OKAN University

2 x 3 participants

2 x 3 participants

host

INKA

host

2 x 1, 2 x 2 participants

4 x 1, 1 x 2 participants

GPOCS

6 x 1 participant

host

6 x 1 participant